Ora Banda Mining (ASX: OBM) has put a $375 million second processing plant at the centre of its plan to more than double gold production at its Davyhurst project in Western Australia to 300,000 ounces a year by FY29.

The 300,000-ounce figure is an aspiration, not a production target. Ora Banda says it does not yet have reasonable grounds to believe it can be achieved, and the company’s own presentations repeat that warning wherever the target appears. The starting point is a record 140,949 ounces produced in FY26, up 53 percent on the 92,399 ounces of FY25.

The new plant will be a standalone 3.0 million tonne per annum facility built beside the existing 1.2Mtpa Davyhurst mill. Together the two mills will lift nameplate capacity by about 250 percent to 4.2Mtpa. Construction is under way and commissioning is expected in the March quarter of 2028.

The board approved the plant in May 2026 at a cost of A$375 million. That covers a A$233 million engineering, procurement and construction contract, with GR Engineering Services as preferred contractor, and about A$142 million of associated works, owner’s costs and contingency. The company expects to incur the costs over FY27 and FY28, funded from existing cash, future cash flow and its debt facility.

The second mill is the hinge of the plan. Davyhurst holds 3.69 million ounces of resources and 610,000 ounces of reserves, and the existing mill is the single processing plant for all of it. A second plant removes the single-mill risk, takes third-party milling costs out of the business, and gives the company room to feed four mines instead of two. Ora Banda was valued at about A$2.3 billion at the close on 26 October 2026.

Ora Banda Managing Director Luke Creagh said: “It is great to see our DRIVE to 300 projects all on schedule as we pursue our aspiration of doubling production to 300,000 ounces and a step-change improvement in unit costs in FY29. Operationally, we are well placed with the underlying performance of our current assets, with weather interruptions and mill downtime that affected performance expected to be limited to the September quarter.”

Four mines, two mills

Riverina and Sand King are the two operating underground mines. Riverina mined 65,684 ounces in FY26 and holds 828,000 ounces of resources, including a 100,000-ounce reserve grading 3.7 grams per tonne gold. Sand King mined 77,886 ounces in FY26 and holds 524,000 ounces of resources, including a 125,000-ounce reserve. The company is targeting consistent annual production of about 100,000 ounces from Sand King.

Waihi is the third underground mine, and the newest. Underground mining began in September 2026, ahead of schedule, and the company expects first high-grade ore from mid-2027. Waihi holds 482,000 ounces of resources and a 101,000-ounce reserve, including the Golden Pole lode at 41,000 ounces grading 5.0 grams per tonne. Golden Pole ore will be treated preferentially through the existing mill while the new plant is built.

Round Dam is the fourth production front. A pre-feasibility study outlines an open pit mining 13.5 million tonnes at 1.7 grams per tonne for 724,000 ounces over about eight years, at a 9.0 to 1 strip ratio and 95 percent metallurgical recovery. Round Dam holds 1.33 million ounces of resources and a 223,000-ounce reserve. A final investment decision is expected in the second half of FY27, with first production targeted for 2028.

Drilling at Waihi has already added a new target. The Midnight prospect, about 500 metres south of the Waihi pit, returned 11.5 metres at 26.0 grams per tonne gold, including 8.9 metres at 32.4 grams per tonne, and 1.6 metres at 65.9 grams per tonne, including 1.0 metre at 104.0 grams per tonne. Drilling through FY27 is targeting extensions to Golden Pole, the main Waihi lode and Midnight.

How it is paid for

Ora Banda ended the September quarter with about A$507 million of liquidity, including A$207 million in cash and an undrawn A$300 million revolving credit facility. The company says the expansion will be funded from cash reserves and future cash flow, with the facility as backup. Growth capital spending in FY27 is guided at A$425 million.

The September quarter shows why the funding matters. Production was 33,305 ounces at an all-in sustaining cost of A$4,214 an ounce, with wet weather and an extended mill shutdown cutting volumes. Gold sold was 33,939 ounces. The company held full-year guidance of 125,000 to 140,000 ounces at A$3,400 to A$3,600 an ounce.

Gold price protection is in place. Put options cover 166,700 ounces at a A$6,000 an ounce floor, at 8,300 ounces a month into 2028. That matters now: spot gold fell below US$3,500 an ounce on 25 November as strong US economic data reinforced bets on higher interest rates, Kitco reported.

Exploration

Exploration is budgeted at A$75 million in FY27, with the same amount planned for each of FY28 and FY29. The resource base has more than doubled since FY23 to 3.69 million ounces, and reserves are up 159 percent in FY26 to 610,000 ounces. The company holds more than 130 kilometres of prospective greenstone strike at Davyhurst.

The next resource on the list is Little Gem. A maiden resource estimate is expected late in the second quarter or early in the third quarter of FY27. Drilling has expanded the mineralised envelope to more than 2.6 kilometres of strike and 750 metres vertically below surface, with a recent intercept of 5.0 metres at 18.1 grams per tonne gold.

The timetable

The test of the plan comes in stages. The Little Gem maiden resource is due around the turn of the year. The Round Dam investment decision follows in the second half of FY27. Waihi’s first high-grade ore is expected from mid-2027. The new mill is due to be commissioned in the March quarter of 2028, with nameplate capacity across both mills targeted for FY29.

If the ounces arrive on that timetable, Ora Banda will be producing at more than twice its FY26 rate. If they do not, the company still has four mines, A$507 million of liquidity and a second mill under construction. The December quarter production report is the next check on whether the ramp is holding.

Sources