Delta Lithium (ASX: DLI) released the first scoping study for its Mt Ida lithium project in Western Australia on 17 November 2026, putting a post-tax net present value of A$748 million and a post-tax internal rate of return of 33% on an 11-year operation.
The plan centres on a one-million-tonne-a-year whole ore flotation (WOF) concentrator producing spodumene, lepidolite and tantalum concentrates. Pre-production capital is estimated at A$483 million, including A$64 million of contingency, with a 4.3-year payback and post-tax free cash flow of A$1,415 million.
The study is preliminary, prepared to an accuracy of plus or minus 40%, and not sufficient to support the estimation of Ore Reserves. Delta states there is no certainty the production target will be realised.
The economics as modelled
The study models 11 years including construction, processing about 8.5 million tonnes of ore at 1.09% lithium oxide. Unit operating costs are put at US$756 per tonne of concentrate, excluding royalties, and peak funding is estimated at about A$498 million. Prices come from Benchmark Minerals Intelligence forecasts, sourced in September 2026 and running to 2042, at an 8% discount rate.
Funding is the open question. Delta says about A$500 million of pre-production funding may be required, with no certainty it can be sourced when needed or without dilution. The company reported cash of A$48.8 million at 30 September 2026, which it says is sufficient to reach a final investment decision, plus about A$100 million of equity in listed entities.
The resource behind the study
The study is based on the Mt Ida resource estimate of 13 November 2025, prepared by Snowden Optiro under the JORC Code: 14.8 million tonnes at 1.21% lithium oxide, 170 parts per million tantalum oxide and 0.42% rubidium oxide, at a cut-off of 0.3% lithium oxide for open pit material and 0.5% underground.
| Category | Tonnes (Mt) | Li2O grade (%) |
|---|---|---|
| Measured | 0.49 | 1.20 |
| Indicated | 7.2 | 1.34 |
| Inferred | 7.1 | 1.07 |
| Total | 14.8 | 1.21 |
The resource covers three pegmatites: Sister Sam (10.4 million tonnes), Timoni (2.0 million tonnes) and Sparrow (2.4 million tonnes). The production target draws on all three categories, including Inferred material, the lowest-confidence category. About 73% of the life-of-mine target is Measured and Indicated, with 27% Inferred. In the first five years, about 83% is Measured and Indicated, covering the 4.3-year payback period.
Three concentrates, not one
The flowsheet is the distinctive part: instead of one spodumene concentrate, the plant recovers lithium into two products and tantalum into a third. At full capacity it is expected to produce about 65,000 tonnes a year of spodumene concentrate (5.5% lithium oxide), about 110,000 tonnes a year of lepidolite concentrate (3.0% lithium oxide, 1.8% rubidium oxide) and about 1,700 tonnes a year of tantalum concentrate (5% tantalum oxide).
Lithium recovery is estimated at about 73% (38% into spodumene, 35% into lepidolite). Tantalum recovery is estimated at 55%, and rubidium recovery into lepidolite at about 60%.
Mining starts in open pits at Sister Sam and Timoni, then moves underground. Sister Sam provides about 75% of the scheduled ore.
Why rubidium matters, and where the risk sits
Rubidium is the unusual part of the Mt Ida story, and the commercial risk. Delta says the project hosts one of the largest and highest-grade publicly released rubidium oxide resources in the world, and the lepidolite concentrate carries the rubidium value. The study applies a rubidium co-product credit to lepidolite revenue based on 5% payability of the current rubidium carbonate price. Most Western governments classify rubidium as a critical mineral, and Delta says demand is assumed to double by 2034. But lepidolite concentrate and its rubidium content need buyers, and Delta lists offtake engagement among its next steps. A rubidium credit tied to a thin market is worth less than a spodumene price set in a liquid one.
Permits, neighbours and what happens next
Mt Ida is fully permitted for open pit and underground mining, and sits about 100 kilometres northwest of Menzies, about 220 kilometres by road from Kalgoorlie. Delta owns 100% of the lithium project; the gold rights belong to Ballard Mining (ASX: BM1), in which it retains about a 30% stake.
Managing Director James Croser said: “The Scoping Study demonstrates that Mt Ida has real potential to be a highly profitable and long-life lithium mine, with valuable tantalum and rubidium co-located within Mt Ida’s lithium orebodies, and only modest additions to the WOF process flowsheet required to bring them to concentrate.”
Next is a pre-feasibility study, with infill drilling to support a maiden Ore Reserve. Delta assumes two to three years to reach a final investment decision, followed by about 15 months of construction.